{"discuss":[{"ddate":"12-Apr-2013 09:16","dcontact":"MDLUuk","dtext":"1) What is different between duration estimates and effort estimates","dtags":"Estimation","darch":"0"},{"ddate":"13-Apr-2013 09:51","dcontact":"MCeWiV","dtext":"Hi Balaji, Assume it will take 1 day(8hrs) with 1 resource to complete a task named de-installation (of a Decommissioning work package) , then , effort estimates for 3 resources would be n times 1 day work , then = 3 x 8hrs = 24hrs","dtags":"Work Contours","darch":"0"}]}